Davis Drive road construction will impact drivers Published June 21, 2011 By Public Affairs 315th Airlift Wing JOINT BASE CHARLESTON, SC -- Beginning June 22, 2011, crews will be repairing and paving portions of Davis Drive from Stewart Avenue to Graves Avenue. To ease the impact to drivers, the project will be split into five phases. The first phase, slated to begin June 22 and continue through July 15, 2011 will be between Stewart and Sloan. Dates are subject to change due to weather and unforeseen issues. One lane will remain open during construction as much as possible. Please limit driving on the affected portions of Davis Drive to essential transit and delivery trucks only. POV's and GOV's should detour to Arthur Drive or Graves Ave if possible. Temporary closures on portions of Davis will occur to allow hot asphalt to cool. Some parking lots may be inaccessible for short periods during construction. Alert aircrew and DFAC parking lots will have at least one entrance open at all times. Please obey posted construction signs, barricades, and flagmen. When driving near construction, be patient, go slow and be safe! If you have any questions or concerns, contact 628 CES POC is 2LT Jordan Leman, 963-8688.